No
Please note the time period for proposals for below-described project has ended. DHHS is no longer accepting proposals for this project.
Project Information
Term of Project:
August 1, 2020 through January 31, 2021
Pre-Proposal Conference
DHHS will host a Pre-Proposal information session on June 26, 2020 at 11:00 AM CT. Entities that are interested in submitting a proposal may participate via WebEx by having a representative attend.
At the Pre-Proposal information session, the DHHS Point of Contact or a designated DHHS representative will provide general information about the funding and answer questions from potential bidders.
Entities can join the WebEx meeting by clicking on the following link:
https://nvcn-cio.webex.com/meet/stephanie.l.beasley
Question and Answer Period
- Questions due to State no later than July 2, 2020 at 5:00 CT. Send questions to
dhhs.rfpquestions@nebraska.gov with email subject of “DCFS Policy / Process Development”.
- Answers to be posted on this page by July 8, 2020 at 5:00 CT.
Due Date for Bids:
July 20, 2020
Post Intent to Award
July 24, 2020
Addenda
-
Questions and Answers
- List of Respondents
- Reject All Bids
Proposals
- Alvarez & Marsal
- BerryDunn
- HMA
Payment Structure
Contractor shall invoice DHHS upon successful completion of deliverables as determined by DHHS. Cost for each deliverable shall be net, including all personnel and travel expenses.
Introduction
The
Division of Children and Family Services (DCFS) needs support in the development and refinement of business processes and our procedures for the following:
- Contract development and approval;
- Business process and best practice recommendations for unique provider agreements serving individual youth;
- Grant writing and development and approval;
- Policy development and use of Standard Operating Procedures (SOPs);
- Central Registry / Expungement of records; and,
- Constituent complaints.
Additionally, a crosswalk of our federal prevention plan, Child and Family Services Plan, the Child and Family Services Review Program Improvement Plan and Family First Prevention Services Act Plan is needed to outline unified goals for prevention, protection, and permanency.
The Contractor will work with DCFS program staff as well as senior leadership and the Director. The final product must include clear guidance outlining an efficient and quality process for the topic areas.
Project Overview and Objectives:
The projects listed above are being developed to ensure there are clear process steps and considerations within each topic area. At this time, DCFS needs refined guidance and areas of responsibility for the areas of contract development, provider agreement process, grant writing / development, policy development, central registry / record expungement and constituent complaints. DCFS has a need for structured business processes to ensure full understanding of the lengthy requirements of each product area as they develop grants, contracts or policy. Process steps should be outlined to ensure compliance with federal law, state statute, regulations, policy and best practice. Internal controls for processes will be outlined in the development of the product.
The Contractor will be required to have robust history and knowledge in child welfare, public assistance, and a history of administrative support and process development. The Contractor must ensure considerations of Nebraska statute, regulation, federal and state policy as well as best practice. The final product will need to provide clear areas of responsibility in each area to ensure clear accountability of implementation.
Scope of Work:
- Review existing processes for:
- Contract development and approval;
- Business process and best practice recommendations for unique provider agreements serving individual youth;
- Grant writing and program development;
- Policy development;
- Central Registry / Expungement of records; and,
- Constituent complaints
- Provide review of regulation, statute, policy, best practice, federal guidance and policy.
- Develop best practice and recommendations for each area.
- Outline best practice, business process, and procedures for policy and expungement of records.
Deliverables
Must be able to complete the outlined deliverables listed below:
- Written guidance documents on the development of the following:
- Contract development and approval;
- Business process and best practice recommendations for unique provider agreements serving individual youth;
- Grant writing and program development;
- Policy development;
- Central Registry / Expungement of records and
- Constituent complaints
- Visual guidance including but not limited to flowcharts, decision trees, etc. in each area of:
- Contract development and approval;
- Business process and best practice recommendations for unique provider agreements serving individual youth;
- Grant writing and program development;
- Policy development;
- Central Registry / Expungement of records; and
- Constituent complaints
- Clear delineation and guidance in use of Standard Work Instruction (SWI) / Standard Operating Procedure (SOP) / Administrative policy;
- Communication plan for field dissemination;
- Plan for embedding changes into training;
- Recommendations for alignment of these processes across program areas of Protection and Safety and Economic Assistance; and,
- Recommendation of structure and timeline for review and continuous internal controls for areas of policy review, regulation review, SOP review.
- Crosswalk of DCFS federal prevention plan, Child and Family Services Plan, the Child and Family Services Review Program Improvement Plan, and Family First Prevention Services Act Plan.
Project Work Plan:
- Bidder must submit with its proposal a Draft Project Work Plan that successfully completes the deliverables outlined above within the project timeframe. The Draft Project Work Plan must include details on what project tasks will be performed face-to-face and what project tasks will be performed virtually.
- No later than two (2) weeks after the project award date, the Contractor must develop and submit to DCFS for approval a Detailed Project Work Plan that includes a schedule, Gantt chart (for all project tasks, subtasks, and activities), and deliverable due dates. The Detailed Project Work Plan must include details on what project tasks will be performed face-to-face and what project tasks will be performed virtually.
Project Mangement
DCFS Director will review and approve revisions within scope and to any deliverable. Revisions that result in additional cost will use the hourly rates provided below and will require a Change Order as specified in in section V.F of the RFQ. Contractor must submit a Scope of Work that includes, at a minimum, a project narrative, position title(s), number of hours, total cost, and due date.